Scope of works

The full PV generator — from unloading to grid integration.

Four coordinated work packages, one team, one responsibility. We tailor the scope to the role split in your EPC contract — from individual packages to the complete PV generator.

MECH

Structure & modules

We deliver

  • Unloading and delivery inspection
  • Support structure assembly
  • PV module installation
  • Row and table labelling

Resources on site

  • Own pile drivers and telehandlers
  • Installation crews with our own foremen
  • Weekly progress reporting
DC

DC installation

We deliver

  • DC cable routes including termination
  • Equipotential bonding and earthing
  • Inverter installation with metering system
  • RS485 communication between inverters

Quality

  • Directly employed, certified electricians
  • Measurements and protocols to the investor's specification
  • Route and string labelling to project standard
AC / MV

AC & medium voltage

We deliver

  • AC cable laying including trenching
  • Medium-voltage cabling with labelling
  • Transformer station foundations
  • Integration with the MV grid

Resources on site

  • Own excavators for cable routes
  • Transformer foundations built with our own resources
  • Coordination with the grid operator via the investor
SITE

Site support

We provide

  • Site management on site (EN / DE / PL)
  • Own machine park — 9 machines
  • Acceptance and as-built documentation

Standard

  • One site manager — one point of contact
  • Documentation to the investor's standard
  • Handover with a complete set of protocols
05 · PROCESS

How a project runs with us

StageWhat happensTypical duration
01 · MobilisationCrew and machines on site, site facilities, H&S documentation, delivery schedule agreed with your site management2–4 weeks from contract
02 · Pile drivingOwn pile drivers, post setting to project tolerances, daily pile logsper project schedule
03 · Structure & modulesSupport structure assembly, module installation, row and table labelling17–20 MWp / month
04 · DC worksCable routes, termination, earthing, inverters, RS485 — with measurement protocolsparallel to stage 03
05 · AC / MVAC cabling incl. trenching, MV works, transformer station foundationsper grid-connection plan
06 · Testing & handoverAs-built documentation, protocols to the investor's standard, acceptance supportuntil signed acceptance
06 · STANDARD

Included in every package

MANAGEMENT

Site management

  • Site manager on site — one point of contact
  • EN / DE / PL speaking supervision
  • Daily coordination with your site management
REPORTING

Progress reporting

  • Weekly progress report with photos
  • Quantities installed vs. schedule
  • Issues flagged within 24 h
HSE

Safety on site

  • Trained foremen, job instructions
  • Housekeeping to the investor's standard
  • Full posting compliance (A1, wages)
DOCS

Documentation

  • Measurement and test protocols
  • As-built documentation
  • Handover package for acceptance

One contractor for the entire PV generator.

From unloading the first delivery to integration with the medium-voltage grid — one team, one contractual responsibility.

Installation capacity17–20 MWp / month
Framework agreement5–10 MW / month
MarketsDE · NL · PL · EU